June

  • Use new Aversive with microb 2007 project [DONE]
  • Commit a new microb 2008 project (based on 2007 code, and removing all unused things). [DONE]

July/August

September

  • study vt100 commands [DONE]
  • do a CLI module with completion [DONE]

October

  • Profiling tool [DONE]
  • Control system debug tool [DONE]
  • New trajectory manager (DONE, but no test at all)

November

  • Control System: make it work with new 2008 code [DONE]
  • Integrate CLI in 2008 code [DONE]
  • CLI: store commands in flash [DONE]
  • Menu : store strings in flash [WON'T BE DONE... use cli only]
  • Use EEPROM to store configuration. [DONE]

December

  • Debug new trajecory manager [DONE]
  • Code and debug new blocking detection module [DONE]
  • Obstacle avoidance integration and optimization [DONE]

January

  • Demonstration of obstacle avoidance using IR sensors [DONE -> not very efficient]
  • Start design of extension board code [DONE]

February

  • Model servo control [DONE]
  • Barrel control [DONE]
  • Catapult control [DONE]
  • Port to 2008 elec [DONE for extension board]
  • All features included in extension board program [DONE]

March

  • Port to 2008 elec [DONE]
  • Start design of camera <-> robot protocol [DONE]
  • Start design of beacons <-> robot protocol [WON'T BE DONE]
  • Test and stress i2c communication [DONE]
  • Certification strategy [DONE]
  • Strategies [WORK IN PROGRESS]

April

  • Tests

May

  • Eurobot